NEW QUESTION # 205
On an agile project, it is important to identify and engage business stakeholders throughout the project and to ensure the team understands the stakeholders' business needs. Which option supports this idea?
- A. A project charter should be established and reviewed throughout the project life cycle to ensure the accurate documentation of stakeholders' interests and expectations.
- B. A user story should be created for all key stakeholders to list their individual business objectives and needs.
- C. An Agile Manifesto should be created to document the project stakeholders, their desired outcomes, and identified risks.
- D. A product backlog should be created to list the project requirements from all of the project stakeholders.
Answer: D
Explanation:
The correct answer is B - A product backlog should be created to list the project requirements from all of the project stakeholders.
In Agile, the product backlog serves as a living document where requirements, user stories, and stakeholder feedback are continuously refined. It is the central mechanism for capturing and prioritizing stakeholder needs and ensuring that business value is delivered incrementally.
From the PMI Agile Practice Guide:
"The product backlog is a prioritized list of work for the development team that is derived from stakeholder input, user stories, and emerging needs. It evolves as the project progresses and stakeholder feedback is incorporated." (PMI Agile Practice Guide, Section 5.2 - Product Backlog) Mike Griffiths writes:
"Product backlogs provide transparency into stakeholder priorities. They enable the team to continuously align work with customer expectations and business needs." (Mike Griffiths, PMI-ACP Exam Prep Book, Chapter 3 - Stakeholder Engagement) Why the other options are incorrect:
* A refers to the traditional project charter, which is not commonly updated throughout the agile life cycle.
* C is a misunderstanding-the Agile Manifesto is a set of principles, not a project-specific document.
* D misuses user stories; stories are used for functional requirements, not stakeholder profiles.
NEW QUESTION # 206
How does Empirical Process Control support Agile methodologies?
- A. Testing, requirements, and adaptation
- B. Visibility, review, and testing
- C. Testing, requirements, and change
- D. Visibility, inspection, and adaptation
Answer: D
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 207
Which of the following best describes a core belief of Agile?
- A. Project status can be gauged by frequently reviewing completed milestones as reflected in the plan.
- B. Unique skill sets are harnessed when team members play different roles on a project.
- C. The best customer feedback comes near the end of the project when there is working software to review.
- D. Working solutions are the most accurate way of seeing the progress of the effort.
Answer: D
NEW QUESTION # 208
Based on the chart, what is the current status of the iteration when comparing story points planned versus completed?
- A. The iteration is in jeopardy.
- B. The team's velocity is constant.
- C. The iteration is ahead of schedule.
- D. The team has removed scope.
Answer: A
NEW QUESTION # 209
Estimating costs for an Agile project starts with which of the following types of meetings?
- A. Project Retrospective
- B. Release Planning
- C. Sprint Planning
- D. Steering Committee
Answer: B
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 210
An agile team identifies that their velocity is lower than predicted, and that their previous forecasts in the product roadmap are wrong. The team is worried that they will be unable to meet a critical release date without corrective action.
What should the team do?
- A. Ask the team lead to calculate the team's target velocity according to the project plan, and assign additional resources to increase capacity.
- B. Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.
- C. Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.
- D. Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.
Answer: B
NEW QUESTION # 211
During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve. What should the team member do?
- A. Work on the next activity, and communicate it to the team during the retrospective.
- B. Notify the product owner and begin resolution.
- C. Immediately begin resolution, and communicate it to the team during the retrospective.
- D. Communicate the issue to the team in the next stand up meeting.
Answer: D
NEW QUESTION # 212
A technique showing Kanban work stages by comparing counted features over a time interval is called a/an:
- A. Fully integrated backlog.
- B. Cumulative flow diagram.
- C. Earned value system.
- D. Progressive elaboration.
Answer: B
Explanation:
Explanation/Reference:
NEW QUESTION # 213
An agile team is unable to complete all its planned sprint user stories, which results in a decrease of its planned sprint velocity. What should the team do?
- A. Re-estimate the incomplete stories for the next sprint because its relative size has changed.
- B. Work with the product owner to create a spike with another agile team.
- C. Re-estimate the sprint's completed stories to increase and adjust the sprint's velocity.
- D. Increase the duration of the next sprint to accommodate the incomplete user stories and maintain velocity.
Answer: A
NEW QUESTION # 214
Risk exposure is the:
- A. Funds set aside to contain the risk.
- B. Probability a risk will occur.
- C. Amount of damage to the project if the risk occurs.
- D. Amount of money the risk will cost if it occurs.
Answer: D
Explanation:
Explanation:
NEW QUESTION # 215
A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?
- A. Place the impacted stories on the story board, and use daily stand-ups to make the product owner aware of the technical issues.
- B. Capture risks and make them visible, and use a burndown chart to focus on reducing risks early in the project.
- C. Seek guidance from the development manager.
- D. Ask the Scrum Master to extend the sprint's duration to allow more time to work through technical issues.
Answer: B
Explanation:
The correct answer is A - Capture risks and make them visible, and use a burndown chart to focus on reducing risks early in the project.
Technical uncertainty is a key area of risk in Agile projects. These risks should be clearly communicated, visualized, and prioritized early in the project to allow timely mitigation. Agile teams are empowered to make decisions and highlight blockers rather than delay work or seek hierarchical intervention.
PMI Agile Practice Guide states:
"Agile teams actively manage risk through transparency and continuous feedback. Risks should be made visible on information radiators and addressed early in the project to prevent impact on value delivery." (PMI Agile Practice Guide, Section 7.3 - Risk Management) Mike Griffiths adds:
"Teams facing uncertainty must surface risks openly and early. Using charts such as risk burndown and dashboards helps keep focus on managing these risks iteratively." (PMI-ACP Exam Prep, Chapter 6 - Problem Detection and Resolution) Incorrect options:
* B contradicts the time-boxing principle of sprints.
* C raises awareness but lacks proactive risk mitigation.
* D introduces a command-and-control dynamic, which is not agile.
NEW QUESTION # 216
No one, not even the Scrum Master, tells the development team how to build the product.
- A. False
- B. True
Answer: B
NEW QUESTION # 217
As user stories are developed, what should be done to record and update acceptance criteria?
- A. Update new tasks in the project plan.
- B. Update current user stories.
- C. Add more user stories.
- D. Use sprint retrospectives.
Answer: C
NEW QUESTION # 218
Which of the following is NOT one of the 12 core practices of XP?
- A. Visualize the flow
- B. System Metaphor
- C. On-site Customer
- D. Coding Standards
Answer: A
NEW QUESTION # 219
At the retrospective, the burndown chart shows that the project is slightly behind schedule. The project team identifies an inexperienced software engineer as the source of reduced velocity-How should the project team address this issue?
- A. Ask the product owner to re-prioritize the user stories at the next retrospective.
- B. Re-estimate the story points with team members at the next iteration planning meeting.
- C. Assign less complex user stories to the inexperienced software engineer at the next iteration planning meeting.
- D. Suggest pair programming during the retrospective.
Answer: D
NEW QUESTION # 220
An agile practitioner wants to ensure that stakeholders have current information about a project's progress.
What should the agile practitioner do?
- A. Frequently update the online project management office (PMO) repository site
- B. Regularly circulate an updated, detailed version of the project plan
- C. Post a project board in an area where all can view it
- D. Invite the stakeholders to daily stand ups
Answer: C
NEW QUESTION # 221
If we plan to work in a two-week iterations with thirteen iterations during the project and the team's velocity will be twenty story points or ideal days per iterations, what will the size of the total project in story points be?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: A
NEW QUESTION # 222
A company is considering developing a new, complex application that will require a large initial investment However if successful the profit potential is high.
When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?
- A. Story points rather than cost estimates
- B. Calculated planned percent complete (PPC)
- C. Many small minimally marketable features (MMFs)
- D. Calculated earned value (EV)
Answer: C
NEW QUESTION # 223
A value stream map is a tool used to identify the:
- A. Waste across the entire process.
- B. Most valuable team interactions.
- C. Highest value product features.
- D. Most likely flow of project risks.
Answer: A
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 224
......